1. Suppose A and B are two points on the opposite banks of a river. The level is set up very near A and after proper temporary adjustment, staff readings are taken at A and B . Suppose the readings are a1 and b1 .2. The level is shifted and set up very near B and after proper adjustment, staff readings are taken at A and B. Technical Data used in the field explained in civil surveyor course in rawalpindi.  Suppose the readings are a1 and b1.3. Let h= true difference of level between A and B.e= combined error due to curvature, refraction and collimation ( The error may be positive or negative, here the error is assumed positive)
In first case; Correct staff reading at A =a1   (as the level is very near A).Correct staff reading at B=b1-e.True difference of level between A and B,H=a1-(b1)(fall from B to A)(1) Some more details of civil surveyor course in rawalpindi are as under.  .In the second case, Correct staff reading at B=b2    (as level is near B)Correct staff reading at B=a2-e.So, true difference of level h = (a2-e) –b2(2)From (1) and (2),2h = a1 – (b1-e) + (-e) - b2 =a1-b1+e+a2-b2= (a1 – b1) + (a2 – b2)h =(a1 – b1) + (a2 –b2)/2It may be observed that the error is eliminated and that the true difference equal to the mean of the two apparent differences of level between A and B.

3.7 PROBLEMS ON RECIPROCAL LEVELLING; Problem 1

In an operation involving reciprocal leveling, two points A and B are taken on opposite banks of a river. When the level was set up near A, the staff readings on A and B were 2.245 and 3.375 respectively. When the level was set up near B, the respective staff readings were 1.955 and 3.055. Find the true difference of level between A and B. What is the RL of B, if that of A is 125.550? Solution In the first setting, Apparent difference of level between A and B = 3.375 – 2.245 = 1.130m (Fall from A to B). . TSK Training for Skills and Knowledge is the best institute in Rawalpindi Islamabad for Pakistani Students who wants to join civil surveyor course in islamabad.

Friday, May 20, 2016

Ethics of a Land Surveyor

civil surveyor course in rawalpindi

Not a lot of people realize that land surveying is actually a fusion of art and science. Yes, different equipment’s are available for the surveyor's use, but the land surveyor still has the last say on the results and that is fully elaborated in civil surveyor course in rawalpindi.
Despite this though, a land surveyor still has several guidelines to follow. If you've had an experience with a dishonest surveyor, or are wary about hiring one, this article should be able to help you out.
civil surveyor course in rawalpindi trains a surveyor should always start a project with fairness in mind. Your client as well as everybody party involved in the project is expecting you to be fair and just so make the best possible assessment with the evidences handed to you.
Before a project commences, the surveyor assigned to the project should come forward if there's a possibility of conflict of interest. This is very important to preserve their relationship with the client. A surveyor should avoid professional impropriety by declaring involvement or any prior affiliations with any of the involved parties. It is also the surveyor's responsibility to keep any information regarding the project as well as the client confidential even after the project is done.
Several cases were reported where the surveyor overcharged the client. This usually happens when the client doesn't know anything about land surveying. A land surveyor running his business with ethics will never do this. Fortunately, there are more honest land surveyors than dishonest ones.
A surveyor should charge a project according to the length of time needed to get it done as well as the level of technical complexity required for it. For the surveyor's sake as well as the client, one should never sign plans, certificates or reports unless these are personally supervised by him. Not only is this unfair on the client's side, doing so could put his reputation in danger should the results get disputed and he doesn't know anything about them.
Just like with other industries, a land surveyor should never undermine the capability of other surveyors or the people from the land surveying industry and if any lacks in quality then he should be recommended civil surveyor course in rawalpindi.
New technologies come up for land surveying all the time. When a surveyor knows that a project is beyond his skills, he should tell the client about it. There's no sense accepting a project only to come up with a subpar result. It will only hurt your business and your reputation.
Surveyors should also be responsible enough to study, do a thorough research, practice and utilize his skills before offering clients a new service. If a surveyor is new to flood determination, for instance, then he needs to make sure that he knows how to perform it before offering it to his clients.
Surveyors do not work alone. They usually have a staff to support them. The land surveyor needs to be responsible for their actions at all cost, for actions or work carried out by them.


Thursday, May 19, 2016

Land Surveying: Ethics of a Land Surveyor

civil surveyor course in rawalpindi

Not a lot of people realize that land surveying is actually a fusion of art and science. Yes, different equipments are available for the surveyor's use, but the land surveyor still has the last say on the results and that is fully elaborated in civil surveyor course in rawalpindi.
Despite this though, a land surveyor still has several guidelines to follow. If you've had an experience with a dishonest surveyor, or are wary about hiring one, this article should be able to help you out.
civil surveyor course in rawalpindi trains a surveyor should always start a project with fairness in mind. Your client as well as everybody party involved in the project is expecting you to be fair and just so make the best possible assessment with the evidences handed to you.
Before a project commences, the surveyor assigned to the project should come forward if there's a possibility of conflict of interest. This is very important to preserve their relationship with the client. A surveyor should avoid professional impropriety by declaring involvement or any prior affiliations with any of the involved parties. It is also the surveyor's responsibility to keep any information regarding the project as well as the client confidential even after the project is done.
Several cases were reported where the surveyor overcharged the client. This usually happens when the client doesn't know anything about land surveying. A land surveyor running his business with ethics will never do this. Fortunately, there are more honest land surveyors than dishonest ones.
A surveyor should charge a project according to the length of time needed to get it done as well as the level of technical complexity required for it. For the surveyor's sake as well as the client, one should never sign plans, certificates or reports unless these are personally supervised by him. Not only is this unfair on the client's side, doing so could put his reputation in danger should the results get disputed and he doesn't know anything about them.
Just like with other industries, a land surveyor should never undermine the capability of other surveyors or the people from the land surveying industry and if any lacks in quality then he should be recommended civil surveyor course in rawalpindi.
New technologies come up for land surveying all the time. When a surveyor knows that a project is beyond his skills, he should tell the client about it. There's no sense accepting a project only to come up with a subpar result. It will only hurt your business and your reputation.
Surveyors should also be responsible enough to study, do a thorough research, practice and utilize his skills before offering clients a new service. If a surveyor is new to flood determination, for instance, then he needs to make sure that he knows how to perform it before offering it to his clients.
Surveyors do not work alone. They usually have a staff to support them. The land surveyor needs to be responsible for their actions at all cost, for actions or work carried out by them.